Public record
Washtenaw County, Michigan. What data centers here promised, and what has been verified as delivered. July to September 2026.
Paid to the resident dividend trust
$1,500,000
About $5.01 per eligible resident this quarter
Paid to the ratepayer rebate pool
$1,250,000
About $4.24 per resident, applied to electric bills
Water not drawn
71.2M gal
Compared with evaporative cooling at the same power use
Heat delivered
52,000 MMBtu
8,400 MWh also exported to the grid at peak
AetherScale Ypsilanti Phase I (100 MW)
Meeting its commitmentsAetherScale Infrastructure Corp. 85 of 100 MW running. Owed this quarter: 3,400.0 credits ($3,400,000).
Resident dividend (cash)$1,500,000 delivered of $1,275,000 owed
Ratepayer rebate (cash)$1,250,000 delivered of $1,062,500 owed
Peak-hour energy export$1,312,500 delivered of $318,750 owed
Public infrastructure funding$300,000 delivered of $255,000 owed
Waste heat delivered$598,000 delivered of $488,750 owed
- Owed
- Delivered
Escrow held: $4,600,000. Credits retired to date: 2,750.
Payments verified
| Date | Paid to | For | Amount | Reference |
|---|---|---|---|---|
| 2026-10-05 | Washtenaw County Resident Dividend Trust | Resident dividend | $1,500,000 | ACH-2026Q3-9981273 |
| 2026-10-05 | Huron Municipal Electric Ratepayer Rebate Pool | Utility rates and grid | $1,250,000 | ACH-2026Q3-9981274 |
| 2026-10-05 | Huron Valley Public Fiber Fund | Waste heat and infrastructure | $300,000 | ACH-2026Q3-9981275 |